Michael Meridith

WTP / WWTP / Underground Utilities
Estimator & Project Manager

WWTP Headworks Modification & Sludge Dewatering System
Lake Wales, FL

Encore Construction Company     Completed October 2003
Project Manager


Headworks modifications included the installation of 2 new slide gates, 1 new JWC Muffin Monster & Screening Auger, aluminum grating.

Sludge Dewatering system consisted of new engineered metal structure over slab on grade, WAS sludge pump & piping, Sludge Flocculator with Polymer feed system, Centrifuge, Screw Press and discharge conveyor.


Click on pictures for larger view

Sludge Dewatering System 
Slab Excavation  Slab FormsSlab Pour conveyor 
erecting building erecting building piping equipment 
processing sludge steel frame roof panel inst finished building 
finished building  finished building
Right click on this
file to view the
Start-Up Video
  
video 
 